BIOMASS CHP FACILITY – NORTHWICH, CHESHIRE

PROJECT OUTLINE:

  • Facility: Waste Treatment Facility at Northwich, Cheshire
  • Chilworth Client: Cobalt Energy Ltd
  • End User Client: DONG Energy
  • Project Value – £50m

PROJECT DETAILS:

Construction of a waste treatment facility, which will separate recyclable materials from household waste and generate green electricity at the same time. The plant uses DONG Energy’s patented REnescience technology and will be the first full-scale bio plant in the world capable of handling household waste through enzymes, mechanical sorting and anaerobic digestion.

CHILWORTH SCOPE OF SERVICES:

Services provided by Chilworth during the Pre-Construction, Construction & Commissioning stages:

Manage and monitor the development of the civils design with the consultant team including the civil and structural engineer; Develop and update the civils cost plan; Programme all of the Civil Works; Manage the Civil Works; Procure and administer the civils trade contracts; Manage the construction variation process for the Civil Works; and Manage overall site Health & Safety.

Northwich
Northwich

Northwich
Northwich

BIOMASS CHP FACILITY – SPEYSIDE, SCOTLAND

PROJECT OUTLINE:

  • Facility: Biomass Combined Heat & Power Plant at Craigellachie, Speyside, Scotland.
  • Chilworth Client: Standardkessel GmbH
  • End User Client: Speyside Renewable Energy Partnership Ltd
  • Project Value – £74m

PROJECT DETAILS:

Construction of a fresh wood biomass Combined Heat and Power plant generating approximately 10MW of electricity and exporting a similar quantity of low pressure steam for use at a whisky distillery. The development uses about 1.5 Ha for buildings and roads and 3.5 Ha for outside wood fuel storage.

CHILWORTH SCOPE OF SERVICES:

Services provided by Chilworth during the Pre-Construction, Construction & Commissioning stages:

Manage and monitor the development of the civils design with the consultant team including the civil and structural engineer; Develop and update the civils cost plan; Programme all of the Civil Works; Manage the Civil Works; Procure and administer the civils trade contracts; Manage the construction variation process for the Civil Works; and Manage overall site Health & Safety.

Speyside
Speyside

Speyside

ENERGY RECOVERY FACILITY – EXETER, DEVON

PROJECT OUTLINE:

  • Facility: Energy Recovery Facility in Exeter, Devon.
  • Chilworth Client: TIRU SA
  • End User Client: Viridor/Devon County Council partnership
  • Project Value – £45m

PROJECT DETAILS:

Construction of an Energy from Waste facility in Exeter. The facility can use up to 60,000 tonnes of non-recyclable household waste to produce 3.5MW of electricity, enough to supply around 5,000 homes.

CHILWORTH SCOPE OF SERVICES:

Services provided by Chilworth during the Pre-Construction, Construction & Commissioning stages:

Manage and monitor the development of the civils design with the consultant team including the civil and structural engineer; Develop and update the civils cost plan; Programme all of the Civil Works; Manage the Civil Works; Procure and administer the civils trade contracts; Manage the construction variation process for the Civil Works; and Manage overall site Health & Safety.

External View

Build Stage