Project Overview

CCM managed all aspects of the civil works (piling, bunker, concrete, steel structures, envelope, building services, fire systems, internal fit out, external works, interface management, quality control, etc) from the enabling works and we are currently in the civils construction phase of the project. The enabling works required ground remediation using a cement/lime soil mixing to provide a stable construction platform.

We also managed the ground contaminated with hydrocarbons to ensure the local environment was protected. Currently the building envelope, building services, fire protection systems and the internal fit out of the control room, electrical rooms and office accommodation are being constructed.

The flexibility of our approach means the project is anticipated to complete on time. To date, no RIDDOR accidents have occurred.

Project Info

Sector

Energy From Waste

Client

Standardkessel GmbH

Period

26 Months

Location

Dundee

Value

£100m

Civils Value

£25m

Results

The project is progressing well and into the final phase of office fit-outs and external works so that hot commissioning can commence. We continue to achieve our goal of zero accidents for the civils working with our construction partners on the scheme.

  • Civil works commenced within one month of NTP
  • Successful installation of ground stabilisation using soil mixing
  • Off-site flood alleviation scheme completed in collaboration with local environmental groups